Hotel Rudrax, Nakhtrana

Check out the below details of Redsun ETC Manifold solar water heater system installed at Hotel Rudrax, Nakhtrana.

Name of Client Hotel Rudrax
Place Nakhtrana
District & State Kutch/ Gujarat
System Capacity 1000 liters per day
Year of Installation 2013
Hot Water Application Bathing , Washing
Previous Using Input Electricity
Electricity saved per Day 46 KWH
Electricity saved per Year 14864 KWH (320 working days )
Average Electricity Cost Rs. 4/unit
Amount Saved per Annum Rs. 59458
Pay Back period of system 2 Years

redsun-solar-at-hotel-rudrax-nakhatrana